Monsoon Cuts Coal Supplies: 45 Indian Power Plants at Risk
India’s power sector is facing mounting fuel pressure as heavy monsoon rains have disrupted coal mining and transport, leaving 45 coal-fired power plants with critically low inventories as of August 25, government data show. Those plants have less than 25% of their required stocks-or under three days of fuel-up from 31 at the end of July, and 40 of the 45 rely mainly on domestic coal, according to the Central Electricity Authority (CEA).
Coal inventories at thermal plants fell about 19% during August, commodities consultancy BigMint told Reuters, to 30.95 million tonnes on August 25, roughly 10 days’ worth of coal burn compared with about 12 days at the end of July. S&P Global reported coal stocks at 34.04 million tonnes on August 18, covering about 11 days and only 55% of the normative requirement; stocks were 34.5% lower than the 51.97 million tonnes recorded on the same date a year earlier.
The stock squeeze has been driven by heavy rainfall in major coal-producing states such as Odisha, Jharkhand and Chhattisgarh, which has slowed mining activity and rail movement to power stations. An NTPC official told Reuters that “coal supplies are running hand-to-mouth,” adding some plants that need five to six coal rakes are receiving only about half that number. A rake is a long set of rail wagons used to move bulk coal; shortages of rakes therefore limit deliveries even when mines have stock.
Weather patterns are compounding the problem. By August 25 India had received about 12% less rainfall than normal, Reuters reported, and on August 24 warned the country may be heading for its weakest monsoon since 2009, with seasonal rainfall potentially ending around 15% below the long-term average as El Niño conditions strengthen. Weaker and uneven rains have reduced hydropower output while hotter conditions have kept electricity demand-particularly for air conditioning-elevated, increasing reliance on thermal generation, especially at night when solar output falls.
The power ministry has asked some coal-fired plants to defer scheduled maintenance to keep units running while fuel availability is uncertain, a senior ministry official told Reuters. Delaying maintenance can preserve capacity in the short term but raises operational risks if units run without planned servicing for extended periods.
Imported coal might relieve some shortages, but delivered costs remain high and imports by power plants fell 22% to 12.28 million tonnes in the first quarter of the 2026–27 financial year, S&P Global said. The broader picture suggests that national coal production has not collapsed-government data indicated higher production in July-but distribution, rail logistics and timing of deliveries are creating a growing disconnect between aggregate supply and plant-level availability. The immediate challenge is getting coal to the right plants at the right time, rather than simply boosting output.