Assam’s Aging Power Grid Strained as Demand Soars — Rs 4,000-cr Upgrade
Guwahati, July 15: Rising power demand in Assam has pushed sections of the state transmission network to critical limits, creating bottlenecks that are undermining the reliability of electricity supply to consumers despite adequate generation and interstate imports. Officials say the system is strained during peak hours and outages are being reported across the state.
Peak demand this season has touched nearly 2,800 MW, and operators report that parts of the transmission grid are reaching operational ceilings. “The present transmission network in Assam is approaching its operational limits due to sustained load growth and aging infrastructure,” official sources said, pointing to thermal overloading, voltage instability and contingency-related constraints on key corridors.
Several 132 kV transmission lines that form the backbone of the lower Assam corridor — Bornagar‑Dhaligaon, Sonabeel‑Depota, Sonabeel‑Ghoramari, Ghoramari‑Depota, Nalbari‑Rangia, Nalbari‑Barpeta and Barpeta‑Dhaligaon — are over three decades old and now operate under significant stress. Sources warned that aging conductors, deteriorating tower hardware and reduced conductor tensile strength have increased line losses and lowered current‑carrying capacity, causing frequent congestion during seasonal and evening peaks.
The older 132 kV conductors have lower ampacity than modern HTLS (high‑temperature, low‑sag) conductors, officials noted, so corridors reach thermal limits before demand can be fully met. These assets also show higher forced‑outage rates from conductor snapping, insulator flashovers, hardware failures and tower deterioration.
Transformation capacity at Samaguri Grid Substation and Salakati BTPS Grid Substation is also said to be inadequate for current and projected loads. Existing transformers are creating evacuation bottlenecks to downstream substations, limiting effective use of available generation and transmission capacity.
During peak loading, system operators are forced to adopt load‑management measures, including load‑shedding, to prevent thermal overloads and voltage collapse. Such measures degrade supply quality for distribution utilities even when power is available at generation and ISTS interfaces.
A government official said grid‑upgrading projects worth over Rs 4,000 crore, including one financed by the Asian Infrastructure Investment Bank (AIIB), are under implementation. He added that these works will take time but are expected to ease constraints once completed.
Officials warned that without timely augmentation, reconductoring and capacity enhancement, the transmission bottlenecks will continue to impair the reliability and quality of power supply across Assam.
Original Source: https://assamtribune.com/assam/aging-grid-soaring-demand-strain-assams-power-network-rs-4000-cr-upgrade-underway-1614282
Category: Assam,Featured
Tags:
Publish Date: 2026-07-15 09:09:00