Assam’s December Deadline: Fix Guwahati’s Long-Delayed Water Supply
Assam Housing and Urban Affairs Minister Kaushik Rai told the Legislative Assembly on July 9 that long-delayed, JICA-funded drinking water projects in Guwahati are now expected to be completed by December this year, more than a decade after work began. Replying to a question from Congress MLA Rekibuddin Ahmed, Rai said the South‑Central Guwahati Water Supply Project has reached 96.75% physical progress and the North Guwahati project 95.75% completion; both projects began in March 2012 and were originally scheduled to finish within 36 and 28 months respectively but suffered prolonged delays.
Rai told the House that a total of Rs 1,450.87 crore has been spent on the two JICA projects, including Rs 1,425.93 crore provided as JICA assistance and Rs 24.95 crore from the State‑Owned Priority Development (SOPD) fund. He said the entire JICA loan component had been utilised by December 2024, and that remaining works are expected to be completed by the end of 2026.
According to the minister, the South‑Central scheme is already supplying potable water to 83,569 households. The North Guwahati scheme, once fully operational, is expected to serve about 15,000 households. Rai also updated the Assembly on other city projects: the South‑West Guwahati Water Supply Project, implemented by the Guwahati Jal Board since October 2023, is 72% complete. That project-estimated at Rs 324.35 crore-is scheduled for completion by mid‑2027.
Rai said the South‑East Guwahati Water Supply Project has finished 17% of its first phase. The initial phase, supported by the Asian Development Bank (ADB), concluded in September 2021; remaining work resumed in March this year with financing from the New Development Bank (NDB). The Rs 192.46 crore project is targeted for completion by May 2029.
The minister also noted legacy and municipal schemes: the Zoo Road Water Supply Scheme, commissioned in 1996 and transferred to the Guwahati Jal Board in 2015, has incurred Rs 75.39 crore in expenditure and currently serves roughly 900 households. The Guwahati Municipal Corporation runs additional supply schemes at Panbazar, Satpukhuri and Kamakhya.
Rai said Rs 3.52 crore was spent on these municipal schemes in the previous financial year, benefitting nearly 21,000 consumers. Citing surveys, he added that Guwahati still requires drinking water connections for about 2.21 lakh households. Work on the JICA‑assisted Guwahati Sewerage Project is also under progress, the minister told the Assembly. (IANS)