Tripura Power Distribution 95% Complete — Major Milestone: Minister
Agartala, 31 May 2026 — Tripura’s Power Minister Ratan Lal Nath said on Sunday that 95% of the state’s distribution-strengthening work, funded by the Asian Development Bank (ADB), has been completed, and that smart meter installation across the state is scheduled to finish by October 2026. He made the announcement during a review meeting at the state guest house chaired by Union Minister for Power, Housing and Urban Affairs Manohar Lal Khattar and Chief Minister Prof. (Dr.) Manik Saha.
Nath said the state has already completed work under the PM-JANMAN scheme and that DA-JGUA projects are 90% complete and expected to be finished by June 2026. He added that remaining loss-reduction work under the RDSS programme is 95% done and will be wrapped up by July 2026.
The minister reported that Tripura’s current peak power demand stands at 542 MW while in-state availability is 365 MW, leaving a shortfall of 177 MW that is currently being met through purchases from the power market. He attributed the constrained availability largely to a shortage of gas supply.
Highlighting improvements in distribution efficiency, Nath said central government assistance helped reduce Aggregate Technical & Commercial (AT&C) losses from 40% in 2018 to 18.23% today. “As per the instructions of the Central Government, work is underway to install smart meters in the state. All 11 kV feeders and distribution transformers have been fitted with smart meters,” he said. To date, 355,158 consumers have been connected to smart meters; the remaining 216,144 consumers will be connected by October 2026, he added.
On prepaid metering, Nath said prepaid meters have been installed in 5,894 government offices. He also stated there are 5,347 stand‑alone prepaid meters and that a total of 159,013 stand‑alone prepaid meters have been installed across Tripura, noting that the state was among the first in India to adopt prepaid meters at scale.
Nath further said that with ADB support, the state has converted the 63 MW open‑cycle gas turbine at Rukhia into a 120 MW combined‑cycle gas turbine at a cost of Rs 1,320 crore; that project is slated for completion by March 2029. Under the Pradhan Mantri Suryaghar Muft Bijli Yojana, he reported, Tripura has installed 12.11 MW of rooftop solar so far against a target of 150 MW.