Skip to content
-
Subscribe to our newsletter & never miss our best posts. Subscribe Now!
Itfy.in

At Itfy, we are dedicated to revolutionizing the way you receive news. Our mission is to provide timely, accurate, and personalized news updates using cutting-edge AI technology. Stay informed, stay ahead with us.

Itfy.in

At Itfy, we are dedicated to revolutionizing the way you receive news. Our mission is to provide timely, accurate, and personalized news updates using cutting-edge AI technology. Stay informed, stay ahead with us.

  • Home
  • News Updates
    • Latest News
    • Entertainment News
    • Northeast News
  • Technology
    • Digital Transformation
    • Artificial Intelligence
    • Machine Learning
    • Generative AI
    • Cybersecurity
  • Education & Growth
    • Education
    • Lifelong Learning
    • Parenting
    • Career Growth
  • Startup & Entrepreneurship
    • Remote Work
    • Startups
    • Digital Marketing
    • Social Media
    • Entrepreneurship
    • Lean Thinking
    • Personal Finance
  • Climate Justice
    • Climate Tech
  • Health & Wellness
    • Mental Health
  • Tourism
  • Home
  • News Updates
    • Latest News
    • Entertainment News
    • Northeast News
  • Technology
    • Digital Transformation
    • Artificial Intelligence
    • Machine Learning
    • Generative AI
    • Cybersecurity
  • Education & Growth
    • Education
    • Lifelong Learning
    • Parenting
    • Career Growth
  • Startup & Entrepreneurship
    • Remote Work
    • Startups
    • Digital Marketing
    • Social Media
    • Entrepreneurship
    • Lean Thinking
    • Personal Finance
  • Climate Justice
    • Climate Tech
  • Health & Wellness
    • Mental Health
  • Tourism
Close

Search

  • https://www.facebook.com/
  • https://twitter.com/
  • https://t.me/
  • https://www.instagram.com/
  • https://youtube.com/
Subscribe
Home/Latest News/Mizoram Infrastructure Push: Lalduhoma Acts on Monsoon Delays
Mizoram Infrastructure Push: Lalduhoma Acts on Monsoon Delays
Latest News

Mizoram Infrastructure Push: Lalduhoma Acts on Monsoon Delays

By adminitfy
August 24, 2026 2 Min Read

Mizoram Chief Minister Lalduhoma on August 24 reviewed the progress of several major state infrastructure projects at a Mi-PRAGATI meeting, where officials flagged monsoon-related delays and outlined measures to keep work on schedule. The review was held at the Chief Minister’s Conference Hall and attended by key ministers and senior officials.

One major item was the proposed Thenzawl Peace City Master Plan in Serchhip district. The planning area covers 85 sq km across six village councils, of which 51.81 sq km has been identified as developable land. Initial works under the plan include a solid waste management system (estimated at Rs 4 crore), development of the Dilpui Lake area (Rs 8 crore) and a new Saturday Market (Rs 3 crore). A further Rs 23 crore has been allocated for rejuvenation of the Lau river and flood mitigation measures in the old town area. The Peace City initiative aims to ease population pressure on Aizawl, with Thenzawl located about 90 km from the state capital.

The meeting also assessed construction of the Central Young Mizo Association (CYMA) Conference Centre at Thingsulthliah near Aizawl, a project under the Ministry of Tourism’s Swadesh Darshan 2.0 scheme with an approved cost of Rs 99.71 crore. Officials reported hill cutting at the site was 80% complete, entry-road cutting 90% complete and exit-road cutting fully finished. The CYMA centre is scheduled for completion by March 2028.

Progress on the Mizo Fiber Grid Network (MFGN) was reviewed as well. The network aims to link all district headquarters via 543 km of Optical Ground Wire and 82 km of aerially deployed optical fibre cable. Sanctioned at Rs 50 crore under the Special Assistance to States for Capital Investment scheme, the project is targeted for completion by December this year; 24 km of Optical Ground Wire have been strung so far.

Officials also discussed the Rs 60 crore integrated office complex at the Mizoram New Capital Complex in Aizawl, reporting 15% completion and noting monsoon conditions have affected construction pace. The 21-km Pukzing–Silsury road in Mamit district, along the Bangladesh border, was reported at 8.38% progress against a Rs 100.24 crore budget. Compensation claims and monsoon-related delays were raised for the road; officials were directed to resolve these issues to keep the project on track for its scheduled January 2028 completion.

Original Source: https://www.indiatodayne.in/mizoram/story/mizorams-big-infrastructure-push-lalduhoma-reviews-projects-hit-by-monsoon-delays-1442253-2026-08-24?utm_source=rssfeed
Category:
Tags:
Publish Date: 2026-08-24 20:12:00

Author

adminitfy

Follow Me
Other Articles
CJP March from India Gate on Sept 5: 'Forced to Return' Protest
Previous

CJP March from India Gate on Sept 5: ‘Forced to Return’ Protest

Transport Workers Lodge Urgent Memorandum to JTC on Auto & E-Rickshaw
Next

Transport Workers Lodge Urgent Memorandum to JTC on Auto & E-Rickshaw

Search...

Recent Posts

  • Horoscope Today, November 20, 2026: Astrological Predictions Revealed
    Horoscope Today, November 20, 2026: Astrological Predictions Revealed
    by adminitfy
    November 20, 2026
  • Empowering Northeast India: CII’s CSR Connect Event Ignites Social Development
    by adminitfy
    July 3, 2024
  • Urgent Crisis: Northeast on High Alert as Death Toll Tragically Rises in Assam
    by adminitfy
    July 3, 2024
  • Triumphant Breakthrough: Security Forces Successfully Capture 4 Insurgents in Manipur Operation
    by adminitfy
    July 3, 2024

Welcome to the ultimate source for fresh perspectives! Explore curated content to enlighten, entertain and engage global readers.

  • Facebook
  • X
  • Instagram
  • LinkedIn

Latest Posts

  • Horoscope Today, November 20, 2026: Astrological Predictions Revealed
  • BBC Cuts Buzz: Next Savings Round Will Be More Noticeable to Audiences-Report Warns What’s Next
  • California Summons Nvidia Over Former CEO’s China Ties
  • The AI Buildout’s Hidden Infrastructure Bill: Power, Permits, and Public Trust
  • Governor Reviews Pakyong’s Major Development Initiatives and Projects
  • November 2026 (614)
  • October 2026 (646)
  • September 2026 (524)
  • August 2026 (1001)
  • July 2026 (986)
  • June 2026 (963)
  • May 2026 (922)
  • April 2026 (1525)
  • March 2026 (1522)
  • February 2026 (1252)
  • January 2026 (968)
  • December 2025 (942)
  • November 2025 (853)
  • October 2025 (869)
  • September 2025 (733)
  • August 2025 (810)
  • July 2025 (720)
  • June 2025 (1244)
  • May 2025 (2201)
  • April 2025 (1481)
  • March 2025 (2020)
  • February 2025 (1159)
  • January 2025 (1440)
  • December 2024 (1499)
  • November 2024 (1771)
  • October 2024 (1815)
  • September 2024 (1750)
  • August 2024 (1458)
  • July 2024 (1268)

Contact

Email

info@itfy.in

Location

INDIA

Copyright 2026 — Itfy.in. All rights reserved.