Guwahati, July 10, 2026 — Assam unveiled an ambitious roadmap on Friday to become a power‑surplus state for the first time, proposing power generation, transmission and storage projects worth more than Rs 77,000 crore in the State Budget for 2026‑27 presented in the Assembly by Finance Minister Jayanta Mallabaruah. The package covers thermal, hydro, solar, pumped storage and grid infrastructure planned over the next few years.
Mallabaruah said the government has drawn up a comprehensive strategy to strengthen the energy sector through both public and private investment. Central to the plan is a mix of large generation projects and supporting transmission and storage to ensure reliable supply and evacuation of power.
Among the headline projects is a proposed 3,200 MW thermal power plant at Bilasipara, estimated to cost Rs 4,000 crore. The state also plans 11 new small hydropower schemes totalling 137.2 MW, with an estimated investment of Rs 2,617 crore across Karbi Anglong, West Karbi Anglong, Udalguri, Dima Hasao, Biswanath and Sivasagar districts.
The Budget approves four pumped storage power (PSP) projects with combined capacity of 4,900 MW and expected private investment of nearly Rs 27,100 crore. The PSP sites are planned at Tharakunchi and Baithalangso (West Karbi Anglong), Howraghat (Karbi Anglong) and Moti Hojai (Dima Hasao). Pumped storage acts as large‑scale battery storage by moving water between reservoirs to store and release energy, supporting grid stability and renewables integration.
Solar generation and battery storage also figure in the plan, including a 50 MW ground‑mounted solar project in Sonitpur, a 25 MW solar project at Namrup in Dibrugarh, and a battery energy storage system in Kamrup to smooth supply and manage peak demand.
To strengthen evacuation and transmission, the Budget allocates roughly Rs 4,600 crore for projects such as a 400 kV evacuation system for the proposed Chapar thermal project, new grid substations at Khumtai and Umrangsu, and modernisation of the Sarusajai substation. Over the next five years the government aims to add 15,000 circuit kilometres of transmission and distribution lines, establish 120 new substations and install 20,000 high‑voltage distribution transformers, while cutting transmission and distribution losses from 13.4 per cent to about 8 per cent.
The Budget also noted that the 120 MW Lower Kopili hydroelectric project has entered trial commissioning and is already supplying around 55 MW to the grid; it is expected to be fully commissioned in July 2026. If delivered as outlined, the combined measures are intended to boost energy security, attract investment and support economic growth across the state.
Original Source: https://assamtribune.com/assam/assam-budget-unveils-rs-77000-crore-roadmap-to-become-power-surplus-state-1614099